Text File  |  1992-12-23  |  1.7 KB  |  53 lines

  1. Newsgroups: sci.space.news
  2. Path: sparky!uunet!spool.mu.edu!agate!ames!dont-send-mail-to-path-lines
  3. From: yee@atlas.arc.nasa.gov (Peter Yee)
  4. Subject: Shuttle Status for 12/23/92 (Forwarded)
  5. Message-ID: <1992Dec24.004200.28692@news.arc.nasa.gov>
  6. Apparently-To: sci-space-news@ames.arc.nasa.gov
  7. Followup-To: sci.space
  8. Originator: yee@atlas.arc.nasa.gov
  9. Sender: usenet@news.arc.nasa.gov
  10. Reply-To: yee@atlas.arc.nasa.gov (Peter Yee)
  11. Organization: NASA Ames Research Center, Moffett Field, CA
  12. Date: Thu, 24 Dec 1992 00:42:00 GMT
  13. Approved: sci-space-news@ames.arc.nasa.gov
  14. Lines: 37
  15.  
  16.                              SPACE SHUTTLE STATUS REPORT
  17.                              Kennedy Space Center, Florida
  18.  
  19.                              Wednesday, December 23, 1992
  20.  
  21.  
  22.           George H. Diller
  23.           407/867-2468
  24.  
  25.           Vehicle: OV-105/Endeavour   Mission Number: STS-54
  26.           Location: Launch Pad 39-B
  27.           Primary Payload: TDRS-F/IUS-13 + Diffuse X-ray Spectrometer (DXS)
  28.           Launch Timeframe: January 13  8:52 a.m. EST
  29.           Mission Duration: 5 Days 23 Hours 33 Minutes
  30.           Inclination: 28.45 degrees   Crew Size: 5
  31.           Nominal Landing: KSC  Jan. 19  8:24 a.m. EST
  32.  
  33.  
  34.           IN WORK TODAY:
  35.  
  36.           - aft main engine compartment closeouts
  37.           - preparations for holiday work suspension/holiday outages
  38.  
  39.  
  40.           WORK COMPLETED:
  41.  
  42.           - Flight Readiness Review (FRR)
  43.           - close and seal crew cabin for the holidays
  44.           - crew cabin leak check
  45.           - close payload bay doors for the holidays
  46.           - power off Space Shuttle vehicle for the holidays
  47.  
  48.  