  1. Newsgroups: sci.space.news
  2. Path: sparky!uunet!think.com!ames!dont-send-mail-to-path-lines
  3. From: yee@atlas.arc.nasa.gov (Peter Yee)
  4. Subject: Shuttle Status for 12/24/92 (Forwarded)
  5. Message-ID: <1992Dec27.211955.28112@news.arc.nasa.gov>
  6. Apparently-To: sci-space-news@ames.arc.nasa.gov
  7. Followup-To: sci.space
  8. Originator: yee@atlas.arc.nasa.gov
  9. Sender: usenet@news.arc.nasa.gov
  10. Reply-To: yee@atlas.arc.nasa.gov (Peter Yee)
  11. Organization: NASA Ames Research Center, Moffett Field, CA
  12. Date: Sun, 27 Dec 1992 21:19:55 GMT
  13. Approved: sci-space-news@ames.arc.nasa.gov
  14. Lines: 110
  15.  
  16.                          SPACE SHUTTLE WEEKLY STATUS SUMMARY
  17.                              Thursday, December 24, 1992
  18.  
  19.           George H. Diller
  20.           Kennedy Space Center
  21.           407/867-2468
  22.  
  23.           Vehicle: OV-105/Orbiter Endeavour   Mission Number: STS-54
  24.           Location: Launch Pad 39-B
  25.           Primary Payload: TDRS-F/IUS-13 + Diffuse X-Ray Spectrometer (DXS)
  26.           Launch Date: January 13  8:52 a.m. EST
  27.           Inclination: 28.45 degrees  Crew Size: 5 astronauts
  28.           Mission Duration: 5 days 23 hours 33 minutes
  29.           Nominal Landing: KSC Jan. 19  8:24 a.m. EST     
  30.  
  31.  
  32.           STS-54 IN WORK:
  33.  
  34.           - No work scheduled until 12:01 a.m. January 4, 1993
  35.  
  36.           STS-54 WORK SCHEDULED:
  37.  
  38.           - resume aft main engine compartment closeouts
  39.           - load mass memory units
  40.           - install EVA spacesuits
  41.           - install flight crew equipment in crew module
  42.           - ordnance connections and stray voltage checks
  43.           - hypergolic tank pressurization
  44.           - external tank purges
  45.           - IUS countdown test/guidance system calibration and alignment
  46.           - TDRS battery charging
  47.           - DXS interim servicing
  48.  
  49.  
  50.           STS-54 WORK COMPLETED:
  51.  
  52.           - close and secure crew cabin access hatch for the holidays
  53.           - close payload bay doors for the holidays
  54.           - install aft compartment flight doors for the holidays
  55.           - power off Space Shuttle vehicle for the holidays
  56.  
  57.  
  58.           Vehicle: OV-102/Orbiter Columbia
  59.           Current location: OPF Bay 2
  60.           Mission: STS-55/Spacelab-D2         Inclination: 28.45 degrees
  61.           Launch timeframe: February, wk 4    Nominal Landing Site: KSC
  62.           Mission Duration: 8 days 22 hours   Crew size: 7
  63.  
  64.           STS-55 IN WORK:
  65.  
  66.           - no work scheduled until January 4, 1993
  67.  
  68.  
  69.           STS-55 WORK SCHEDULED:
  70.  
  71.           - resume standard tile repair
  72.           - resume payload bay cleaning
  73.           - resume freon coolant loop functional tests
  74.           - install Spacelab tunnel
  75.           - install Spacelab D-2 laboratory module
  76.  
  77.           STS-55 WORK COMPLETED:
  78.  
  79.           - forward reaction control system installation/connects/checkout
  80.           - OMS pod leak and functional checks
  81.           - hydraulic system servicing/leak and functional checks
  82.           - drage chute intsllation
  83.           - GAS beams installed
  84.           - Spacelab tunnel adapter installation
  85.           - main landing gear functional test
  86.           - freon closed-loop coolant system leak checks
  87.           - main engine mechanical and electrical connections
  88.           - freon coolant loop rework
  89.  
  90.           SPECIAL TOPICS: STS-55 VAB High Bay 3 -  During high pressure
  91.           checks of the left booster, leakage was seen at the left forward
  92.           center joint.  The booster segement was destacked and a hair 1
  93.           1/10 inches long was found across the secondary O-ring seal.  The
  94.           booster segment will be restacked and retested after the holidays
  95.           with no schedule impact to launch.
  96.  
  97.  
  98.           Vehicle: OV-103/Discovery   Mission Number: STS-56
  99.           Location: OPF Bay 3
  100.           Payloads: ATLAS-2/ODERACS/SSBUV/SPARTAN/SUVE
  101.           Launch timeframe: March, wk 3   Crew Size: 5
  102.           Mission Duration: 8 days   Inclination: 57 degrees
  103.           Nominal Landing Site: KSC
  104.  
  105.  
  106.           STS-56 IN WORK:
  107.  
  108.           - No work scheduled until January 4, 1993
  109.  
  110.  
  111.           STS-56 WORK COMPLETED:
  112.  
  113.           - orbiter safed/hypergolic residual deservicing complete
  114.           - removal of forward reaction control system
  115.           - removal of ferry flight tail cone
  116.           - removal of USAF airborne support equipment
  117.           - open payload bay doors
  118.           - orbiter/ODERACS interface troubleshooting
  119.           - ODERACS removal
  120.  
  121.  
  122.           STS-56 WORK SCHEDULED: