  1. Path: sparky!uunet!dtix!darwin.sura.net!zaphod.mps.ohio-state.edu!magnus.acs.ohio-state.edu!usenet.ins.cwru.edu!agate!ames!dont-send-mail-to-path-lines
  2. From: yee@atlas.arc.nasa.gov (Peter Yee)
  3. Newsgroups: sci.space.news
  4. Subject: Shuttle Status for 12/21/92 (Forwarded)
  5. Message-ID: <1992Dec23.054648.2450@news.arc.nasa.gov>
  6. Date: 23 Dec 92 05:46:48 GMT
  7. Sender: usenet@news.arc.nasa.gov
  8. Reply-To: yee@atlas.arc.nasa.gov (Peter Yee)
  9. Followup-To: sci.space
  10. Organization: NASA Ames Research Center, Moffett Field, CA
  11. Lines: 61
  12. Approved: sci-space-news@ames.arc.nasa.gov
  13. Apparently-To: sci-space-news@ames.arc.nasa.gov
  14. Originator: yee@atlas.arc.nasa.gov
  15.  
  16.  
  17.                              SPACE SHUTTLE STATUS REPORT
  18.                              Kennedy Space Center, Florida
  19.  
  20.                              Monday, December 21, 1992
  21.  
  22.  
  23.           George H. Diller
  24.           407/867-2468
  25.  
  26.           Vehicle: OV-105/Endeavour   Mission Number: STS-54
  27.           Location: Launch Pad 39-B
  28.           Primary Payload: TDRS-F/IUS-13 + Diffuse X-ray Spectrometer (DXS)
  29.           Launch Timeframe: NET January 13
  30.           Mission Duration: 5 Days 23 Hours 33 Minutes
  31.           Inclination: 28.45 degrees   Crew Size: 5
  32.           Nominal Landing Site: KSC
  33.  
  34.           IN WORK TODAY:
  35.  
  36.           - IUS ordnance installation
  37.           - IUS flight battery installation
  38.           - Space Shuttle vehicle ordnance installation
  39.           - aft compartment closeouts
  40.           - preparations for holiday work suspension/holiday outages
  41.  
  42.  
  43.           WORK COMPLETED:
  44.  
  45.           - IUS Flight Readiness Checks
  46.           - retest IUS Range Safety hold-fire circuit
  47.           - calibration of inertial measurement units
  48.           - crew cabin and aft compartment cleaning
  49.           - avionics bay closeouts
  50.           - aft main engine compartment confidence test
  51.  
  52.  
  53.           WORK SCHEDULED:
  54.  
  55.           - Flight Readiness Review on Tuesday
  56.           - close payload bay doors for the holidays on Tuesday night
  57.           - power down Space Shuttle vehicle for the holidays on Wednesday
  58.  
  59.  
  60.           SPECIAL TOPICS:
  61.  
  62.                OV-103/Discovery atop the 747 Shuttle Carrier Aircraft
  63.           arrived at KSC at 2:41 p.m. EST on Friday.  It was demated from
  64.           the 747 and arrived at OPF Bay 3 at 7:25 a.m. on Saturday.  The
  65.           orbiter has been jacked and leveled.  The forward reaction
  66.           control system (FRCS) has been removed and is to be transported
  67.           to the Hypergolic Maintenance Facilty (HMF) today.  Also in work
  68.           today is the removal of the ferry flight tail cone.  The payload
  69.           bay doors are being opened for removal of the airborne support
  70.           equipment which will be followed by troubleshooting of ODERACS.
  71.  
  72.                In the Vehicle Assembly Building, STS-55 solid rocket
  73.           booster stacking and leak checks of the left and right boosters
  74.           was successfully completed on Saturday.  Joint closeouts are in
  75.           work.  Mating the external tank is scheduled to occur when work
  76.           resumes after the Christmas holidays.
  77.