- Newsgroups: comp.software-eng
- Path: sparky!uunet!zaphod.mps.ohio-state.edu!cis.ohio-state.edu!news.sei.cmu.edu!mcp
- From: mcp@sei.cmu.edu (Mark Paulk)
- Subject: Re: Appeal to SEI (was: Debugging the process)
- Message-ID: <1992Dec28.113148.15707@sei.cmu.edu>
- Keywords: "sei cmm" "sw engineering" "process improvement" "sw quality"
- Sender: netnews@sei.cmu.edu (Netnews)
- Organization: Software Engineering Institute
- References: <1992Dec22.164508.2582@csi.uottawa.ca> <1992Dec22.201249.23289@den.mmc.com> <Bzp0KE.8xL@NeoSoft.com>
- Date: Mon, 28 Dec 1992 11:31:48 EST
- Lines: 15
-
- What we intend the CMM to say is that an organization has to have a good
- metrics program in place to achieve level 4.
-
- We do not say that an organization cannot, or should not, have metrics in
- place much earlier. In fact, some specific measurements are called out in the
- CMM at each level, although we try not to overspecify what measures or require
- an organizational measurement program at level 2.
-
- The belief that the SEI requires that "you have to be level 4 to do
- measurement" is a fairly widespread misconception that we have tried
- repeatedly to correct. It's about as explicit in CMM v1.1 as we can say it.
-
- Mark C. Paulk
- Software Engineering Institute
- Carnegie Mellon University, Pittsburgh, PA 15213-3890
-