- --sample.dat
- --::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
- TRACKER REDESIGN 256Sam Harbaugh 6 71985 5 311 2 40
- HI LEVEL D 15.0 1 0.0TRUE
- DETAIL DES 20.0 2 0.0TRUE
- CODE 25.0 3 0.0TRUE
- UNIT TEST 20.0 3 0.0TRUE
- INTEGRATE 20.0 3 0.0TRUE
- 1 1 2191985GENERIC PACKAGES, TRACKER DRIVERS FINISHED
- 2 2 3151985MENUS, MENU DRIVER, READ/WRITE TO FILE
- 3 3 5 31985PROMPTING AND REPORT GENERATION WORKS
- MAY LEE ML 2.50040 2311902 2311902 2311902 2311902 2311902 2311902
- BONNIE BURKHARDT BB 2.50040 2311902 2311902 2311902 2311902 2311902 2311902
- AMY ARNESON AA 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- CATHY CARLSON CC 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- DAN DILLON DD 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- ELVIN EDGEWORTH EE 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- FAYE FUDGE FF 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- GEORGE GILSETH GG 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- HARVEY HARRISON HH 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- WILLIAM WILLIAMSON WW 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- ROBIN ROGERS RR 1.00040 2311902 2311902 2311902 2311902 2311902 2311902
- TRACKER 0.030003000300030003000
- INPREP 0.030003000300030003000
- CALENDAR PACKAGE CALNDRTRACKER 1 1 140 0 1401.0DDDDD 6101985 2221985FBB
- LIST PACKAGE LISTPKINPREP 1 1 100 0 1231.0DDDDD 6 91985 2221985FML
- DATA PACKAGE DATAPKINPREP 1 1 100 0 1301.0DDDDD 6101985 2221985TMLMLMLMLBB
- VT100 AND MENUS VT100 INPREP 1 2 400 0 5031.0DDDDD 6 91985 2221985FML
- PROMPTS PROMPTINPREP 1 2 800 0 12051.0DDDDD 6 91985 2221985FML
- TRACKER TRACKRTRACKER 2 1 250 0 861.0D9774 6111985 2221985FBB
- INITIALIZE TRACKER INITTRINPREP 2 2 30 0 141.0DDD98 6101985 2221985FML
- SET UP TRACKER SETUP INPREP 2 2 30 0 341.0DDD99 6101985 2221985FML
- MANIPULATE DATA MANDATINPREP 2 2 70 0 351.0DD988 6101985 2221985FML
- PRIORITIZE PRIOR TRACKER 2 2 150 0 921.0DD954 6121985 2221985FBB
- CALCULATE TIME DONE CALCTITRACKER 2 3 100 0 1111.0DDD99 6101985 2221985FAA
- CHECK AC TOTAL PERCENT CHKPCTINPREP 2 2 30 0 331.0DDD98 6101985 2221985FAA
- GROUP DATA FIXES FIXDATINPREP 3 3 70 0 771.0DDD65 6191985 4121985FBB
- RESET ENTIRE DATA RESET INPREP 3 3 30 0 301.0DD74 6191985 4121985FBB
- UPDATE ORIGINAL TO CURRENT SIZE ORIGFXINPREP 3 3 10 0 101.0DDDDD 6191985 4121985FBB
- WRITE DATA WRDATAINPREP 2 2 20 0 201.0DDDDD 6101985 4 51985FML
- MENU DRIVER MENUDRINPREP 1 2 130 0 1441.0DDDDD 6 91985 4 51985FML
- GET DATA FROM FILE GETDATINPREP 1 1 35 0 291.0DDDDD 6 91985 4 51985FML
- GLOBAL DATA PKG GLOBALINPREP 3 3 75 0 481.0DDD95 6111985 4121985FAA
- ACTIVITY PKG AC INPREP 3 3 500 0 2411.0DDD87 6121985 4121985FML
- MILESTONE PKG MS INPREP 3 3 450 0 2001.0DD973 6141985 4121985FML
- PERSONNEL PKG PR INPREP 3 3 500 0 3701.0DD965 6201985 4121985FML
- SUBSYSTEM PKG SS INPREP 3 3 350 0 1771.0DDD74 6211985 4121985FML
- ELEMENT PKG EL INPREP 3 3 550 0 5811.0DD877 6281985 4121985TMLMLMLBBBB
- REPORT DRIVER REPORTTRACKER 1 1 100 0 1211.0DDDDD 6101985 4 51985FBB
- CALC PERCENT DONE CALPCTTRACKER 2 2 140 0 1201.0DD988 6131985 4 51985FBB
- REPORT COMMENTS RCOMMNTRACKER 2 2 35 0 341.0DDD6 6101985 4 51985FML
- REPORT DATE DONE BY MS RDATDNTRACKER 3 3 150 0 1501.0DD74 6281985 4121985FBB
- REPORT ALL ELEMENTS RLSTELTRACKER 2 2 150 0 1561.0DDD84 6141985 4 51985FBB
- REPORT EL BY MILESTONE RLSTMSTRACKER 2 2 175 0 1901.0DDD87 6151985 4 51985FBB
- REPORT EL BY PERSON RLSTPRTRACKER 2 2 175 0 1711.0DDD99 6151985 4 51985FBB
- REPORT EL BY SUBSYSTEM RLSTSSTRACKER 2 2 175 0 1791.0DDD97 6181985 4 51985FBB
- REPORT NEW PAGE RPAGE TRACKER 2 1 30 0 301.0DDDDD 6111985 4 51985FBB
- REPORT PARAMETER DATA RPARAMTRACKER 3 3 250 0 2491.0DD775 7 31985 4121985FBB
- REPORT PCT DONE BY SUBSYSTEM RPCTSSTRACKER 3 3 150 0 1061.0DD875 7 41985 4121985FBB
- LIST OF REPORTS PRINTED RPRINTTRACKER 3 3 26 0 261.0DDDDD 6281985 4121985FML
- REPORT MILSTONE SUMMARY RSUMMSTRACKER 3 3 125 0 1161.0DDD87 7 51985 4121985FBB
- REPORT SUBSYSTEM SUMMARY RSUMSSTRACKER 3 3 125 0 1161.0DDD87 7 51985 4121985FBB
- REPORT WORK DISTRIBUTION RDIST TRACKER 3 3 150 0 1391.0DD776 7 91985 4121985FBB
- REPORT WORK BY SUBSYSTEM RBYSS TRACKER 3 3 150 0 1201.0DD764 7111985 4121985FBB
- --::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
- --sample.rpt
- --::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
- .page
- .hl2 Parameter Data Report
- .lit
- Project Name: TRACKER REDESIGN #256 Status Date: 4/12/1985
- Project Manager: Sam Harbaugh
- NUMBER OF ACTIVITIES : 5
- NUMBER OF MILESTONES : 3
- NUMBER OF PERSONNEL : 2
- NUMBER OF SUBSYSTEMS : 2
- NUMBER OF ELEMENTS : 40
-
- SUBSYSTEM % AVAILABLE AT START
- --------- --------------------
- TRACKER 0.00%
- INPREP 0.00%
-
- PERSON'S NAME INITIALS RATE PER HOUR HOURS PER WEEK START DATE STOP DATE
- ------------- -------- ------------- -------------- ---------- ----------
- MAY LEE ML 2.500 40 0/ 0/ 0 99/99/99
- BONNIE BURKHARDT BB 2.500 40 0/ 0/ 0 99/99/99
-
- ACTIVITY NAME % TOTAL PROJECT PRIORITY CONSIDERED % AVAILABLE AT START
- ------------- --------------- -------- ---------- --------------------
- HI LEVEL D 15.00% 1 YES 0.00%
- DETAIL DES 20.00% 2 YES 0.00%
- CODE 25.00% 3 YES 0.00%
- UNIT TEST 20.00% 3 YES 0.00%
- INTEGRATE 20.00% 3 YES 0.00%
-
- TASK NUMBERS
- HI L DETA CODE UNIT INTE
- ---- ---- ---- ---- ----
- 3000 3000 3000 3000 3000
- 3000 3000 3000 3000 3000
-
- MILESTONE DUE DATE DESCRIPTION
- --------- ---------- -----------
- 1 2/19/1985 GENERIC PACKAGES, TRACKER DRIVERS FINISHED
- 2 3/15/1985 MENUS, MENU DRIVER, READ/WRITE TO FILE
- 3 5/ 3/1985 PROMPTING AND REPORT GENERATION WORKS
-
-
- MILESTONE COMPLETION SEQUENCE
-
- 1 2 3
-
- .el
- .page
- .hl2 Comments Report
- .lt
- TRACKER COMMENTS
- ====================================================================================================================================
- A copy of any comments file may be included in this report.
- .el
- .page
- .hl2 All Element Status Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** ALL ELEMENT STATUS REPORT ***
-
-
-
- ** ACTIVITIES ** ORIGINL CURRENT EQ. NEW SIZE LST
- MS PR SUBSYSTEM DESCRIPTION ABREV RP H D C U I SIZE SIZE SIZE VERIFIED COMPXY
- -- -- --------- ----------- ------ -- - - - - - ------- ------- ------- -------- ------
- 1 1 TRACKER CALENDAR PACKAGE CALNDR BB D D D D D 140 140 140 2/22/85 1.000
- 1 1 INPREP LIST PACKAGE LISTPK ML D D D D D 100 123 123 2/22/85 1.000
- 1 1 INPREP DATA PACKAGE DATAPK ML D D D D * 100 130 130 2/22/85 1.000
- BB * * * * D
- 1 2 INPREP VT100 AND MENUS VT100 ML D D D D D 400 503 503 2/22/85 1.000
- 1 2 INPREP PROMPTS PROMPT ML D D D D D 800 1205 1205 2/22/85 1.000
- 2 1 TRACKER TRACKER TRACKR BB D 9 7 7 4 250 86 86 2/22/85 1.000
- 2 2 INPREP INITIALIZE TRACKER INITTR ML D D D 9 8 30 14 14 2/22/85 1.000
- 2 2 INPREP SET UP TRACKER SETUP ML D D D 9 9 30 34 34 2/22/85 1.000
- 2 2 INPREP MANIPULATE DATA MANDAT ML D D 9 8 8 70 35 35 2/22/85 1.000
- 2 2 TRACKER PRIORITIZE PRIOR BB D D 9 5 4 150 92 92 2/22/85 1.000
- 2 3 TRACKER CALCULATE TIME DONE CALCTI BB D D D 9 9 100 111 111 2/22/85 1.000
- 2 2 INPREP CHECK AC TOTAL PERCENT CHKPCT ML D D D 9 8 30 33 33 2/22/85 1.000
- 3 3 INPREP GROUP DATA FIXES FIXDAT BB D D D 6 5 70 77 77 4/12/85 1.000
- 3 3 INPREP RESET ENTIRE DATA RESET BB D D 7 4 30 30 30 4/12/85 1.000
- 3 3 INPREP UPDATE ORIGINAL TO CURRENT SIZE ORIGFX BB D D D D D 10 10 10 4/12/85 1.000
- 2 2 INPREP WRITE DATA WRDATA ML D D D D D 20 20 20 4/ 5/85 1.000
- 1 2 INPREP MENU DRIVER MENUDR ML D D D D D 130 144 144 4/ 5/85 1.000
- 1 1 INPREP GET DATA FROM FILE GETDAT ML D D D D D 35 29 29 4/ 5/85 1.000
- 3 3 INPREP GLOBAL DATA PKG GLOBAL ML D D D 9 5 75 48 48 4/12/85 1.000
- 3 3 INPREP ACTIVITY PKG AC ML D D D 8 7 500 241 241 4/12/85 1.000
- 3 3 INPREP MILESTONE PKG MS ML D D 9 7 3 450 200 200 4/12/85 1.000
- 3 3 INPREP PERSONNEL PKG PR ML D D 9 6 5 500 370 370 4/12/85 1.000
- 3 3 INPREP SUBSYSTEM PKG SS ML D D D 7 4 350 177 177 4/12/85 1.000
- 3 3 INPREP ELEMENT PKG EL ML D D 8 * * 550 581 581 4/12/85 1.000
- BB * * * 7 7
- 1 1 TRACKER REPORT DRIVER REPORT BB D D D D D 100 121 121 4/ 5/85 1.000
- 2 2 TRACKER CALC PERCENT DONE CALPCT BB D D 9 8 8 140 120 120 4/ 5/85 1.000
- 2 2 TRACKER REPORT COMMENTS RCOMMN ML D D D 6 35 34 34 4/ 5/85 1.000
- 3 3 TRACKER REPORT DATE DONE BY MS RDATDN BB D D 7 4 150 150 150 4/12/85 1.000
- 2 2 TRACKER REPORT ALL ELEMENTS RLSTEL BB D D D 8 4 150 156 156 4/ 5/85 1.000
- 2 2 TRACKER REPORT EL BY MILESTONE RLSTMS BB D D D 8 7 175 190 190 4/ 5/85 1.000
- 2 2 TRACKER REPORT EL BY PERSON RLSTPR BB D D D 9 9 175 171 171 4/ 5/85 1.000
- 2 2 TRACKER REPORT EL BY SUBSYSTEM RLSTSS BB D D D 9 7 175 179 179 4/ 5/85 1.000
- 2 1 TRACKER REPORT NEW PAGE RPAGE BB D D D D D 30 30 30 4/ 5/85 1.000
- 3 3 TRACKER REPORT PARAMETER DATA RPARAM BB D D 7 7 5 250 249 249 4/12/85 1.000
- 3 3 TRACKER REPORT PCT DONE BY SUBSYSTEM RPCTSS BB D D 8 7 5 150 106 106 4/12/85 1.000
- 3 3 TRACKER LIST OF REPORTS PRINTED RPRINT ML D D D D D 26 26 26 4/12/85 1.000
- .el
- .page
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** ALL ELEMENT STATUS REPORT ***
-
-
-
- ** ACTIVITIES ** ORIGINL CURRENT EQ. NEW SIZE LST
- MS PR SUBSYSTEM DESCRIPTION ABREV RP H D C U I SIZE SIZE SIZE VERIFIED COMPXY
- -- -- --------- ----------- ------ -- - - - - - ------- ------- ------- -------- ------
- 3 3 TRACKER REPORT MILSTONE SUMMARY RSUMMS BB D D D 8 7 125 116 116 4/12/85 1.000
- 3 3 TRACKER REPORT SUBSYSTEM SUMMARY RSUMSS BB D D D 8 7 125 116 116 4/12/85 1.000
- 3 3 TRACKER REPORT WORK DISTRIBUTION RDIST BB D D 7 7 6 150 139 139 4/12/85 1.000
- 3 3 TRACKER REPORT WORK BY SUBSYSTEM RBYSS BB D D 7 6 4 150 120 120 4/12/85 1.000
- ------- ------- ------- -------- ------
- TOTALS 7026 6456 6456 1.000
- .el
- .page
- .hl2 List by Subsystem Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** LIST BY SUBSYSTEM REPORT ***
- TRACKER
-
-
- ** ACTIVITIES ** ORIGINL CURRENT EQ. NEW SIZE LST MAN-HRS
- MS PR DESCRIPTION ABREV RP H D C U I SIZE SIZE SIZE VERIFIED COMPXY TO COMP
- -- -- ----------- ----- -- - - - - - ------- ------- ------- -------- ------ -------
- 1 1 CALENDAR PACKAGE CALNDR BB D D D D D 140 140 140 2/22/85 1.00 0.0
- 2 1 TRACKER TRACKR BB D 9 7 7 4 250 86 86 2/22/85 1.00 9.5
- 2 2 PRIORITIZE PRIOR BB D D 9 5 4 150 92 92 2/22/85 1.00 9.0
- 2 3 CALCULATE TIME DONE CALCTI BB D D D 9 9 100 111 111 2/22/85 1.00 1.8
- 1 1 REPORT DRIVER REPORT BB D D D D D 100 121 121 4/ 5/85 1.00 0.0
- 2 2 CALC PERCENT DONE CALPCT BB D D 9 8 8 140 120 120 4/ 5/85 1.00 5.0
- 2 2 REPORT COMMENTS RCOMMN ML D D D 6 35 34 34 4/ 5/85 1.00 3.8
- 3 3 REPORT DATE DONE BY MS RDATDN BB D D 7 4 150 150 150 4/12/85 1.00 23.7
- 2 2 REPORT ALL ELEMENTS RLSTEL BB D D D 8 4 150 156 156 4/ 5/85 1.00 10.0
- 2 2 REPORT EL BY MILESTONE RLSTMS BB D D D 8 7 175 190 190 4/ 5/85 1.00 7.6
- 2 2 REPORT EL BY PERSON RLSTPR BB D D D 9 9 175 171 171 4/ 5/85 1.00 2.7
- 2 2 REPORT EL BY SUBSYSTEM RLSTSS BB D D D 9 7 175 179 179 4/ 5/85 1.00 5.7
- 2 1 REPORT NEW PAGE RPAGE BB D D D D D 30 30 30 4/ 5/85 1.00 0.0
- 3 3 REPORT PARAMETER DATA RPARAM BB D D 7 7 5 250 249 249 4/12/85 1.00 23.4
- 3 3 REPORT PCT DONE BY SUBSYSTEM RPCTSS BB D D 8 7 5 150 106 106 4/12/85 1.00 8.9
- 3 3 LIST OF REPORTS PRINTED RPRINT ML D D D D D 26 26 26 4/12/85 1.00 0.0
- 3 3 REPORT MILSTONE SUMMARY RSUMMS BB D D D 8 7 125 116 116 4/12/85 1.00 4.6
- 3 3 REPORT SUBSYSTEM SUMMARY RSUMSS BB D D D 8 7 125 116 116 4/12/85 1.00 4.6
- 3 3 REPORT WORK DISTRIBUTION RDIST BB D D 7 7 6 150 139 139 4/12/85 1.00 12.0
- 3 3 REPORT WORK BY SUBSYSTEM RBYSS BB D D 7 6 4 150 120 120 4/12/85 1.00 13.2
- ------- ------- ------- -------- ------ -------
- TOTALS 2746 2452 2452 1.00 145.6
- .el
- .page
- .hl2 List by Milestone Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** LIST BY MILESTONE REPORT ***
- Milestone # 2 is due 3/15/85 -- MENUS, MENU DRIVER, READ/WRITE TO FILE
-
-
- ** ACTIVITIES ** ORIGINL CURRENT EQ. NEW SIZE LST MAN-HRS
- PR SUBSYSTEM DESCRIPTION ABREV RP H D C U I SIZE SIZE SIZE VERIFIED COMPXY TO COMP
- -- --------- ----------- ------ -- - - - - - ------- ------- ------- -------- ------ -------
- 1 TRACKER TRACKER TRACKR BB D 9 7 7 4 250 86 86 2/22/85 1.00 9.5
- 1 TRACKER REPORT NEW PAGE RPAGE BB D D D D D 30 30 30 4/ 5/85 1.00 0.0
- 2 INPREP INITIALIZE TRACKER INITTR ML D D D 9 8 30 14 14 2/22/85 1.00 0.3
- 2 INPREP SET UP TRACKER SETUP ML D D D 9 9 30 34 34 2/22/85 1.00 0.5
- 2 INPREP MANIPULATE DATA MANDAT ML D D 9 8 8 70 35 35 2/22/85 1.00 1.5
- 2 TRACKER PRIORITIZE PRIOR BB D D 9 5 4 150 92 92 2/22/85 1.00 9.0
- 2 INPREP CHECK AC TOTAL PERCENT CHKPCT ML D D D 9 8 30 33 33 2/22/85 1.00 0.8
- 2 INPREP WRITE DATA WRDATA ML D D D D D 20 20 20 4/ 5/85 1.00 0.0
- 2 TRACKER CALC PERCENT DONE CALPCT BB D D 9 8 8 140 120 120 4/ 5/85 1.00 5.0
- 2 TRACKER REPORT COMMENTS RCOMMN ML D D D 6 35 34 34 4/ 5/85 1.00 3.8
- 2 TRACKER REPORT ALL ELEMENTS RLSTEL BB D D D 8 4 150 156 156 4/ 5/85 1.00 10.0
- 2 TRACKER REPORT EL BY MILESTONE RLSTMS BB D D D 8 7 175 190 190 4/ 5/85 1.00 7.6
- 2 TRACKER REPORT EL BY PERSON RLSTPR BB D D D 9 9 175 171 171 4/ 5/85 1.00 2.7
- 2 TRACKER REPORT EL BY SUBSYSTEM RLSTSS BB D D D 9 7 175 179 179 4/ 5/85 1.00 5.7
- 3 TRACKER CALCULATE TIME DONE CALCTI BB D D D 9 9 100 111 111 2/22/85 1.00 1.8
- ------- ------- ------- -------- ------ -------
- TOTALS 1560 1305 1305 1.00 58.3
- .el
- .page
- .hl2 List by Person Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** LIST BY PERSON REPORT ***
- MAY LEE
-
-
- ** ACTIVITIES ** ORIG CURRNT EQ NEW MAN-HRS FINISH DUE
- MS PR SUBSYSTEM DESCRIPTION ABREV H D C U I SIZE SIZE SIZE CPX TO COMP DATE DATE
- -- -- --------- ----------- ----- - - - - - ------ ------ ------ --- ------- -------- --------
- 1 1 INPREP LIST PACKAGE LISTPK D D D D D 100 123 123 1.0 0.0 DONE 2/19/85
- 1 1 INPREP DATA PACKAGE DATAPK D D D D * 100 130 130 1.0 0.0 DONE 2/19/85
- 1 1 INPREP GET DATA FROM FILE GETDAT D D D D D 35 29 29 1.0 0.0 DONE 2/19/85
- 1 2 INPREP VT100 AND MENUS VT100 D D D D D 400 503 503 1.0 0.0 DONE 2/19/85
- 1 2 INPREP PROMPTS PROMPT D D D D D 800 1205 1205 1.0 0.0 DONE 2/19/85
- 1 2 INPREP MENU DRIVER MENUDR D D D D D 130 144 144 1.0 0.0 DONE 2/19/85
- 2 2 INPREP INITIALIZE TRACKER INITTR D D D 9 8 30 14 14 1.0 0.3 4/15/85 3/15/85
- 2 2 INPREP SET UP TRACKER SETUP D D D 9 9 30 34 34 1.0 0.5 4/15/85 3/15/85
- 2 2 INPREP MANIPULATE DATA MANDAT D D 9 8 8 70 35 35 1.0 1.5 4/15/85 3/15/85
- 2 2 INPREP CHECK AC TOTAL PERCENT CHKPCT D D D 9 8 30 33 33 1.0 0.8 4/15/85 3/15/85
- 2 2 INPREP WRITE DATA WRDATA D D D D D 20 20 20 1.0 0.0 DONE 3/15/85
- 2 2 TRACKER REPORT COMMENTS RCOMMN D D D 6 35 34 34 1.0 3.8 4/15/85 3/15/85
- 3 3 INPREP GLOBAL DATA PKG GLOBAL D D D 9 5 75 48 48 1.0 2.3 4/16/85 5/ 3/85
- 3 3 INPREP ACTIVITY PKG AC D D D 8 7 500 241 241 1.0 9.6 4/17/85 5/ 3/85
- 3 3 INPREP MILESTONE PKG MS D D 9 7 3 450 200 200 1.0 18.0 4/19/85 5/ 3/85
- 3 3 INPREP PERSONNEL PKG PR D D 9 6 5 500 370 370 1.0 30.3 4/25/85 5/ 3/85
- 3 3 INPREP SUBSYSTEM PKG SS D D D 7 4 350 177 177 1.0 12.7 4/29/85 5/ 3/85
- 3 3 INPREP ELEMENT PKG EL D D 8 * * 550 581 581 1.0 62.7 5/ 3/85 5/ 3/85
- 3 3 TRACKER LIST OF REPORTS PRINTED RPRINT D D D D D 26 26 26 1.0 0.0 DONE 5/ 3/85
- ----- ------ ------ --- ------- -------- --------
- TOTALS 4231 3947 3947 1.0 142.7
- .el
- .page
- .hl2 Subsystem Summary Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** SUBSYSTEM SUMMARY REPORT ***
-
-
-
- MAN-HRS PERCENT
- SUBSYSTEM ML BB TO COMP COMPLETE
- --------- ------- ------- ------- --------
- TRACKER 3.8 141.8 145.6 85.16%
- INPREP 115.7 49.8 165.5 92.14%
- ------- ------- ------- --------
- TOTALS: 119.5 191.6 311.1 89.48%
- .el
- .page
- .hl2 Milestone Summary Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** MILESTONE SUMMARY REPORT ***
-
-
-
- MAN-HRS PERCENT
- MILESTONE ML BB TO COMP COMPLETE
- --------- ------- ------- ------- --------
- 1 0.0 0.0 0.0 100.00%
- 2 7.0 51.3 58.3 88.83%
- 3 84.6 128.6 213.3 80.65%
- ------- ------- ------- --------
- TOTALS: 91.6 180.0 271.6 89.48%
- .el
- .page
- .hl2 Lines of Code per Subsystem Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** LINES OF CODE PER SUBSYSTEM ***
-
-
-
- ORIGINAL CURRENT EQ. NEW OLDEST MOST RECENT
- SUBSYSTEM SIZE SIZE SIZE VERIFICATION VERIFICATION
- --------- -------- -------- -------- ------------ ------------
- TRACKER 2746 2452 2452 2/22/1985 4/12/1985
- INPREP 4280 4004 4004 2/22/1985 4/12/1985
- -------- -------- -------- ------------ ------------
- TOTALS: 7026 6456 6456 2/22/1985 4/12/1985
-
- .el
- .page
- .hl2 Percent Complete Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** ORIGINAL ESTIMATE OF PERCENT COMPLETE WITHIN SUBSYSTEM ***
-
-
-
- % DONE % AVAIL %ENTIRE
- SUBSYSTEM HI LEVE DETAIL CODE UNIT TE INTEGRA CONTRACT AT START PROJECT
- --------- ------- ------- ------- ------- ------- -------- -------- -------
- TRACKER 100.00% 99.09% 87.47% 75.71% 59.92% 83.81% 0.00% 83.81%
- INPREP 100.00% 100.00% 94.84% 81.74% 71.46% 89.35% 0.00% 89.35%
- --------- ------- ------- ------- ------- ------- -------- -------- -------
- TOTALS ON
- CONTRACT: 100.00% 99.64% 91.96% 79.38% 66.95% 87.19% 0.00% 87.19%
-
- % AVAIL
- START: 0.00% 0.00% 0.00% 0.00% 0.00%
-
- % ENTIRE
- PROJECT: 100.00% 99.64% 91.96% 79.38% 66.95%
- .el
- .page
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** CURRENT ESTIMATE OF PERCENT COMPLETE WITHIN SUBSYSTEM ***
-
-
-
- % DONE % AVAIL %ENTIRE
- SUBSYSTEM HI LEVE DETAIL CODE UNIT TE INTEGRA CONTRACT AT START PROJECT
- --------- ------- ------- ------- ------- ------- -------- -------- -------
- TRACKER 100.00% 99.65% 89.17% 77.27% 62.40% 85.16% 0.00% 85.16%
- INPREP 100.00% 100.00% 95.36% 86.21% 80.27% 92.14% 0.00% 92.14%
- --------- ------- ------- ------- ------- ------- -------- -------- -------
- TOTALS ON
- CONTRACT: 100.00% 99.87% 93.01% 82.81% 73.48% 89.48% 0.00% 89.48%
-
- % AVAIL
- START: 0.00% 0.00% 0.00% 0.00% 0.00%
-
- % ENTIRE
- PROJECT: 100.00% 99.87% 93.01% 82.81% 73.48%
- .el
- .page
- .hl2 Distribution of Work Remaining within Subsystem Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** ORIGINAL DISTRIBUTION OF WORK REMAINING WITHIN SUBSYSTEM ***
- (in MAN-HOURS)
-
-
- TOTAL PERCENT
- SUBSYSTEM HI LEVEL DETAIL D CODE UNIT TES INTEGRAT REMAINING COMPLET
- --------- -------- -------- -------- -------- -------- --------- -------
- TRACKER 0.0 2.0 34.4 53.4 88.0 177.8 83.81%
- INPREP 0.0 0.0 22.1 62.5 97.7 182.3 89.35%
- -------- -------- -------- -------- -------- --------- -------
- TOTALS: 0.0 2.0 56.5 115.9 185.8 360.1 87.19%
-
- % OF TOTAL: 0.00% + 0.56% + 15.69% + 32.18% + 51.58% = 100.00%
- .el
- .page
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** CURRENT DISTRIBUTION OF WORK REMAINING WITHIN SUBSYSTEM ***
- (in MAN-HOURS)
-
-
- TOTAL PERCENT
- SUBSYSTEM HI LEVEL DETAIL D CODE UNIT TES INTEGRAT REMAINING COMPLET
- --------- -------- -------- -------- -------- -------- --------- -------
- TRACKER 0.0 0.7 26.6 44.6 73.8 145.6 85.16%
- INPREP 0.0 0.0 18.6 44.2 63.2 126.0 92.14%
- -------- -------- -------- -------- -------- --------- -------
- TOTALS: 0.0 0.7 45.1 88.8 137.0 271.6 89.48%
-
- % OF TOTAL: 0.00% + 0.25% + 16.62% + 32.69% + 50.44% = 100.00%
- .el
- .page
- .hl2 Completion Date for Milestones Report
- .lt
- Project Name: TRACKER REDESIGN
-
- Project Manager: Sam Harbaugh
-
- Status Date: 4/12/85
-
-
-
-
- *** COMPLETION DATE FOR MILESTONES ***
-
-
-
- MILE- PREVIOUS CURRENT DUE
- STONE ML BB COMPL DATE COMPL DATE DATE
- ----- -------- -------- ---------- ---------- --------
- 1 DONE DONE 4/ 8/85 DONE 2/19/85
- 2 4/15/85 4/23/85 4/18/85 4/23/85 3/15/85
- 3 5/ 3/85 5/16/85 5/15/85 5/16/85 5/ 3/85
- -------- -------- ---------- ---------- --------
- TOTAL: 5/ 3/85 5/16/85 5/16/85
-
- .el
- .page
- .hl2 Reports Printed List
- .lt
- REPORTS PRINTED
- ====================================================================================================================================
-
-
-
- Parameter Data List
- Tracker Comments
- All Element Status Report
- List By Subsystem
- List By Milestone
- List By Person
- Subsystem Summary
- Milestone Summary
- Work Units Per Subsystem
- Percent Completion Of Work Within Subsystem
- Distribution Of Remaining Work Within Subsystems
- Completion Date For Milestones
- .end lit
-
-