home *** CD-ROM | disk | FTP | other *** search
/ Internet 1996 World Exposition / park.org.s3.amazonaws.com.7z / park.org.s3.amazonaws.com / Netherlands / pavilions / techno / svk / engels / werking / werk2.asc < prev   
Encoding:
INI File  |  2017-09-22  |  14.5 KB  |  542 lines

  1. [Image]
  2. [Backward] [Home]
  3.  
  4. [Index]
  5. [Visitors' book]
  6.  
  7. [animation]
  8.  
  9. [animation] Operation of the Storm Surge Barrier 
  10.  
  11. Trusses
  12.  
  13. The trusses, each 240 metres in length,
  14. are a prominent visual part of the Storm
  15. Surge Barrier. Their function is to
  16. transmit directly to the ball-joint the
  17. loads exerted on the retaining walls in
  18. the closure process. During closure the
  19. truss will ride up and by approximately
  20. 40 centimetres into a camber, levelling
  21. out again when the load eases. 
  22.  
  23.                          1. Dimensions
  24.                          2. Loads
  25.                          3. Manufacture
  26.                          4. Assembly
  27.                          5. Attachment to the retaining wall [Image]
  28. [Backward] [Home]
  29.  
  30. [Index]
  31. [Visitors' book]
  32.  
  33. Truss dimensions
  34.  
  35. Each arm consists of two separate open-
  36. frame girders joining up at the ball-
  37. joint. 
  38.  
  39. Length:                                      240 metres
  40. Maximum height:                              20 metres
  41. Main girder cross-section: 1.80 metres
  42. Main girder wall-thickness:40-90 mm
  43. Diagonals cross-section:                     60-80 mm
  44. Diagonals wall-thickness:  12-30 cm
  45. Maximum compressive force: 300 MN
  46. Tensile force (given
  47. negative thrust):                            50 MN
  48. Connection with hinge:                       - end-diagonal
  49.                                              - tailpiece
  50. Camber:                                       8 cm
  51.  
  52. The trusses were constructed with a
  53. camber of 500 mm. After removal of the
  54. supports a camber of 80 mm remained. 
  55.  
  56. [camber]
  57. [Image]
  58. [Backward] 
  59.  
  60. [Home]
  61. [Index]
  62.  
  63. [Visitors' book]
  64.  [photo of arm]
  65.  
  66.  
  67. Truss loads
  68.  
  69. The loads on the trusses have been
  70. calculated with the aid of an influencing
  71. factor model (i.e. the finite elements
  72. model), in which the trusses - like the
  73. retaining wall - form part of an integral
  74. model of the total sector-gate. The model
  75. translates a unit of (bar) force on a
  76. given section of the retaining wall into
  77. bar forces in the truss. The hydraulic
  78. loads on the retaining wall are translated
  79. into a combination of unit loads; in this
  80. way the maximum and minimum normal forces
  81. in the truss can be determined. 
  82.  
  83. Apart from the hydraulic loads and the
  84. dead-weight of the truss, the loads
  85. imposed on the arms by wind, temperature,
  86. snow and ice-formation have also been
  87. allowed for in the calculations. 
  88. [Image] [Backward]
  89. [Home] [Index]
  90.  
  91. [Visitors' book]
  92. [photo of welding]
  93. Truss manufacture
  94.  
  95. The main girders of the truss consist of
  96. 4-metre cylinders. These cylinders were
  97. rolled out of straight plates and then
  98. welded longitudinally. By means of a U-
  99. butt joint the cylinders were joined
  100. together to form girders of up to 60
  101. metres in length. The main girders of
  102. the truss were supplied in 60-metre
  103. lengths. These sections were joined up
  104. at the construction site and the
  105. diagonals affixed between the girders.
  106. The diagonals of the open-frame consists
  107. of spiral-shaped welded pipes,
  108. constructed along the same lines as the
  109. cardboard tube inside a toilet roll. 
  110.  
  111. [Image] [Background]
  112. [Home] [Index]
  113.  
  114. [Visitors' book]
  115. [photo of pipe]
  116.  
  117. [photo train]  Truss assembly 
  118.  
  119. Assembly at the construction site
  120. commenced with the positioning of
  121. temporary supports, on which the lower
  122. cylinder-girders of the truss were
  123. placed. Temporary supports or "A-
  124. frames" were then placed on the lower
  125. two main girders. Mobile cranes then
  126. lifted the upper girder sections into
  127. position, after which the diagonals
  128. were positioned between the upper and
  129. lower girders. The truss-sections were
  130. then welded together. On account of
  131. the wall-thickness (up to 90 mm) of
  132. the main girders, a single weld
  133. consisted of 102 layers, taking
  134. approximately 160 welding-hours. To
  135. permit welding under controlled
  136. conditions and to prevent pollution of
  137. the surface waters, welding tents were
  138. positioned around these connection-
  139. points, with lighting and dust-
  140. exhaustion facilities. 
  141.      
  142.  
  143. [Image]
  144. [Backward] [Home]
  145.  
  146. [Index]
  147. [Visitors' book]
  148.  
  149. [photo of wall]
  150.  
  151. Attachment of the trusses to the
  152. retaining wall
  153.  
  154. The trusses are attached to the retaining
  155. wall when the latter is floating. By the
  156. admission of ballast water into the gate,
  157. by controlling the dock and outer water
  158. level and by manoeuvring with the aid of
  159. winches, the retaining wall is positioned
  160. in such a way that the first three main
  161. girders of the truss can be attached. The
  162. main girders were fixed in position by
  163. means of clamps. The retaining wall is
  164. once again manoeuvred in such a way that
  165. the three remaining main girders can be
  166. affixed in the correct position. All the
  167. main girders are then welded to the
  168. retaining wall. Finally the clamping
  169. structures are removed and the remaining
  170. diagonals, bottom props and the coupling-
  171. girder are positioned. 
  172.  
  173. [Image] [Backward]
  174. [Home] [Index]
  175.  
  176. [Visitors' book] Operation of the Storm Surge Barrier
  177.  
  178. Wetted works (sill structure)
  179.  
  180. The sill structure on the bottom of the
  181. New Waterway has three functions:
  182.  
  183.  *                        The formation of a flat base and
  184.                           foundation for the retaining walls,
  185.                           which are positioned on the sill-
  186.                           blocks with the aid of fenders.
  187.  *                        Cutting down the flow of water once
  188.                           the barrier is closed.
  189.  *                        Holding in place the subgrade on
  190.                           which the blocks are based. 
  191.  
  192. 1.                        Sill-blocks
  193. 2.                        Bottom protection and filter-bed
  194. 3.                        Dredging works
  195. 4.                        Raking the surface
  196. 5.                        Dumping the filter-bed   
  197.  
  198. [Image]
  199. [Backward]
  200.  
  201. [Home]
  202. [Index]
  203.  
  204. [Visitors' book]
  205.  
  206.  
  207.  
  208.  
  209.  
  210.  
  211.  
  212.  
  213.  
  214.  
  215.  
  216.  
  217.  
  218.  
  219.  
  220.  
  221.  
  222.  
  223. [Image]
  224. [Backward]
  225. Wetted works sill-blocks
  226.  
  227. A total of 64 sill-blocks have been
  228. installed on the bottom of the fast-
  229. flowing New Waterway at an average
  230. distance of 3.5 centimetres apart. The
  231. blocks were delivered by pontoon and
  232. positioned with the aid of a floating
  233. derrick. Various measuring instruments
  234. were used to enable the blocks to be
  235. positioned to within one centimetre.
  236. A 21-metre-high measuring tower was
  237. attached to each block, which remained
  238. just poking up above water after the block
  239. had been sunk into position. 
  240.  
  241. Since the sills are somewhat curved, the
  242. blocks are slightly wedge-shaped. In
  243. cross-section the blocks are also flared,
  244. thus preventing the tops of the blocks
  245. from "rubbing" against each other in such
  246. a way as to create a larger crack at the
  247. bottom than permitted. Two rubber toes
  248. have been fitted on one side of each
  249. block, with corresponding notches on the
  250. other side.    [Home]
  251. [Index]
  252.  
  253. [Visitors' book] Wetted works - bottom protection and
  254. filter-bed
  255.  
  256. It was not possible for the sill-blocks to
  257. be simply placed direct onto the river-
  258. bed: rapid accelerations in current would
  259. otherwise create major turbulence beneath
  260. and in the vicinity of the blocks upon
  261. closure of the barrier. Furthermore the
  262. sill could be seriously destabilised if
  263. water were unable to pass beneath the sill
  264. blocks. For this reason the blocks rest on
  265. a porous filter-bed, in turn resting on
  266. substantial bottom-protection. 
  267.  
  268. Filter-bed
  269.  
  270. Length:                      60 metres
  271. Weight:                      206 MN (206,000 tonnes)
  272.                              various materials,
  273.                              distributed over four layers:
  274. layer 1                      sand      0.5-5 mm  
  275.                                        thickness 0.5 m
  276.                                        (bottom layer)
  277. layer 2                      gravel    3.5-35 mm 
  278.                                        thickness 0.5 m
  279. layer 3                      (basalt)  30-140 mm 
  280.                                        thickness 0.5 m
  281. layer 4                      rubble (basalt) 10-60 kg 
  282.                                        thickness 0.75 m (top
  283.                                        layer)
  284.  
  285. [Image]
  286. [Backward]
  287.  
  288. [Home]
  289. [Index]
  290.  
  291. [Visitors' book]
  292. Wetted works - dredging works
  293.  
  294. In order to install the filter-bed and the
  295. bottom-protection, the new Waterway was
  296. dredged out from a depth of 14.5 metres
  297. below Amsterdam Ordnance Datum (NAP) to a
  298. maximum depth of 22.5 metres below NAP. In
  299. total 920,000 cubic metres of sand and
  300. sludge were dredged up. With the
  301. installation of the filter-bed the bottom
  302. was raised to a level of 17 metres below
  303. NAP. 
  304.  
  305. Three kinds of dredging vessels were used:
  306.  
  307.  *                      The tow-hopper for the coarse-
  308.                         dredging of the cunette (trench) in
  309.                         the New Waterway. A backhoe or grab
  310.                         was used to dredge the slopes. 
  311.  *                      The dustpan suction-dredger for
  312.                         smoothing the cunette and installing
  313.                         the bottom filter-layer. 
  314.  *                      The inclined stone-tipper for dumping
  315.                         the bottom protection and the other
  316.                         two filter-layers. 
  317. [Image]
  318. [Background]
  319.  
  320. [Home]
  321. [Index]
  322.  
  323. [Visitors' book]
  324.  
  325.  
  326.  
  327.  
  328.  
  329.  
  330. [Image]
  331. [Backward] Wetted works - raking out
  332.  
  333. A good seal was needed between the filter
  334. bed and the sill blocks. This was achieved
  335. by smoothing the top layer of the filter-
  336. bed. To this end a steel device with
  337. vertical teeth was mounted on the mouth of
  338. a dustpan suction-dredger to create a kind
  339. of rake. Following the good results
  340. obtained with a similar method on Neeltje
  341. Jans and in the Petroleum Harbour in the
  342. Europort area, this method was also
  343. applied in the New Waterway. 
  344. [Home]
  345. [Index]
  346.  
  347. [Visitors' book]
  348. Wetted works - dumping the filter-bed
  349.  
  350. After extensive research it was considered
  351. feasible to dump the various filter
  352. materials on the river bed. This procedure
  353. involved two risks:
  354.  
  355.  *                      the risk of separation of the filter
  356.                         material (with larger particles
  357.                         becoming separated from smaller),
  358.                         thus potentially reducing the
  359.                         stability of the filter-bed. 
  360.  *                      the risk of mixing in sand when the
  361.                         filter material was dumped; the
  362.                         deposition of sludge between the
  363.                         various layers also reduces the
  364.                         stability of the filter-bed. 
  365.  
  366. Special measuring techniques were used in
  367. the dumping-process. It proved possible to
  368. dump the various layers on each other to
  369. within 10 centimetres of the required
  370. thickness. 
  371.  
  372. Vessels
  373. Various vessels were used in installing
  374. the filter-bed. A dredge was fitted out in
  375. order to suck up sand and to dump coarse
  376. sand and gravel. Another vessel (Jetsed)
  377. squirted air and water jets to prevent any
  378. sludge from being deposited between the
  379. various layers. The Jetsed is a self-
  380. propelling vessel that removes sediment
  381. deposits in the cunette between the filter
  382. layers. This is achieved by vertical air
  383. and water injection, thus throwing up the
  384. disturbed sediment, which is then borne
  385. away in the tidal currents. 
  386. [Image]
  387. [Backward] [Home]
  388.  
  389. [Index]
  390. [Visitors' book]
  391.  
  392. [animation]
  393.  
  394. [animation]
  395.  
  396. [animation]
  397.  
  398. [animation] Operation of the Storm Surge Barrier
  399.  
  400. Operating equipment and parking dock
  401.  
  402. Upon closure of the barrier, operating
  403. equipment drives the retaining walls out
  404. of the parking dock to close the New
  405. Waterway. This equipment is operated from
  406. control buildings on the north and south
  407. sides. The equipment consists of three
  408. elements: the operating equipment of the
  409. dock-gate, the locomobile and the ballast
  410. system in the retaining wall. 
  411.  
  412.  
  413. [Image]
  414. [Backward] [Home]
  415.  
  416. [Index]
  417. [Visitors' book]
  418.  
  419. [photo of dock]
  420.  
  421. [photo of dock]
  422.  
  423. Operating equipment parking dock
  424.  
  425. [detail of parking dock]
  426. The parking dock protects the retaining
  427. wall when the Storm Surge Barrier is
  428. retracted, thus creating a protected
  429. harbour for the retaining wall. When
  430. inside the dock the retaining wall cannot
  431. be rammed by passing vessels. With this
  432. in mind the dock has also been fitted
  433. with a special, extremely robust gate. 
  434.  
  435. One of the great advantages of the
  436. present Storm Surge Barrier design is
  437. that when at rest, the parking docks are
  438. dry, so that maintenance activities can
  439. be easily carried out. To facilitate
  440. maintenance still further, 14 concrete of
  441. support points have been installed in and
  442. beside the dock, thus leaving the wall
  443. some 2.5 metres off the floor of the
  444. dock. 
  445.  
  446. [Image]
  447. [Backward]
  448.  
  449. [Home]
  450. [Index]
  451.  
  452. [Visitors' book]
  453. [animation]
  454. Operating equipment - dock-gate
  455.  
  456. [dock-gate]
  457. The dock-gate is designed to seal off the
  458. dock. In addition the dock-gate protects
  459. the retaining wall from being run into by
  460. vessels; the gate has been designed in
  461. such a way that vessels scraping the gate
  462. are warded off, while also providing
  463. maximum protection in the event of a head-
  464. on collision. The dock-gate may be
  465. compared with a safe-door (dimensions: 2 m
  466. thick, 12 m high and 20 m long), running
  467. backwards and forwards over a rail. Since
  468. sludge builds up on the rail, the dock-
  469. gate is opened once a month for the sludge
  470. to be bulldozered off.
  471.  
  472. The dock-gate is opened immediately before
  473. the retaining wall is propelled into the
  474. main stream. Once the closure has been
  475. completed the dock-gate seals off the
  476. parking dock again. 
  477. [Image]
  478. [Backward]
  479.  
  480. [Home]
  481. [Index]
  482.  
  483. [Visitors' book]
  484. [animation]
  485.  
  486. [animation]
  487.  
  488. [animation]
  489. Operating equipment - the locomobile 
  490.  
  491. [locomobile]
  492. In order to close the barrier, the
  493. locomobile on top pushes the retaining
  494. wall horizontally out of the parking dock.
  495. Upon completion of the closure the
  496. locomobile draws the retaining wall back
  497. into the dock. With the aid of running and
  498. guide wheels on railtracks, the locomobile
  499. rests with its own weight on the upper
  500. side of the retaining wall. It pushes off
  501. against the control tower and transmits
  502. its force to the retaining wall by means
  503. of a rack and pinion. The toothed wheels
  504. are constructed out of high-grade chrome
  505. nickel steel. The rack runs the entire
  506. length of the door. 
  507.  
  508. In the rest situation the locomobile also
  509. keeps the retaining wall in position
  510. horizontally. 
  511. [Image]
  512. [Backward]
  513.  
  514. [Home]
  515. [Index]
  516.  
  517. [Visitors' book]
  518. Operating equipment - ballast system 
  519.  
  520. During closure the retaining walls move in
  521. two directions. Apart from the horizontal
  522. movement out of the parking dock the walls
  523. also move up and down in the waves when
  524. being sunk and refloated. The ballast
  525. system in the retaining wall facilitates
  526. the sinking and refloating of the
  527. retaining wall. When the remote-controlled
  528. inlet-valves are opened, water flows into
  529. the specially designed ballast tanks in
  530. the retaining wall. In order to ensure
  531. that the wall sinks stably, the water must
  532. flow into all the tanks evenly. 
  533.  
  534. Pumps set in the retaining wall expel the
  535. ballast water from the retaining wall when
  536. the latter needs to be raised again. Each
  537. retaining wall is fitted with 30 pumps and
  538. 14 chaser-pumps to remove the last
  539. remaining water. The capacity of the pumps
  540. varies from 1.6 kW to 40 kW.
  541.  
  542.