home *** CD-ROM | disk | FTP | other *** search
INI File | 2017-09-22 | 14.5 KB | 542 lines |
- [Image]
- [Backward] [Home]
-
- [Index]
- [Visitors' book]
-
- [animation]
-
- [animation]Operation of the Storm Surge Barrier
-
- Trusses
-
- The trusses, each 240 metres in length,
- are a prominent visual part of the Storm
- Surge Barrier. Their function is to
- transmit directly to the ball-joint the
- loads exerted on the retaining walls in
- the closure process. During closure the
- truss will ride up and by approximately
- 40 centimetres into a camber, levelling
- out again when the load eases.
-
- 1. Dimensions
- 2. Loads
- 3. Manufacture
- 4. Assembly
- 5. Attachment to the retaining wall[Image]
- [Backward] [Home]
-
- [Index]
- [Visitors' book]
-
- Truss dimensions
-
- Each arm consists of two separate open-
- frame girders joining up at the ball-
- joint.
-
- Length: 240 metres
- Maximum height: 20 metres
- Main girder cross-section: 1.80 metres
- Main girder wall-thickness:40-90 mm
- Diagonals cross-section: 60-80 mm
- Diagonals wall-thickness: 12-30 cm
- Maximum compressive force: 300 MN
- Tensile force (given
- negative thrust): 50 MN
- Connection with hinge: - end-diagonal
- - tailpiece
- Camber: 8 cm
-
- The trusses were constructed with a
- camber of 500 mm. After removal of the
- supports a camber of 80 mm remained.
-
- [camber]
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
- [photo of arm]
-
-
- Truss loads
-
- The loads on the trusses have been
- calculated with the aid of an influencing
- factor model (i.e. the finite elements
- model), in which the trusses - like the
- retaining wall - form part of an integral
- model of the total sector-gate. The model
- translates a unit of (bar) force on a
- given section of the retaining wall into
- bar forces in the truss. The hydraulic
- loads on the retaining wall are translated
- into a combination of unit loads; in this
- way the maximum and minimum normal forces
- in the truss can be determined.
-
- Apart from the hydraulic loads and the
- dead-weight of the truss, the loads
- imposed on the arms by wind, temperature,
- snow and ice-formation have also been
- allowed for in the calculations.
- [Image] [Backward]
- [Home] [Index]
-
- [Visitors' book]
- [photo of welding]
- Truss manufacture
-
- The main girders of the truss consist of
- 4-metre cylinders. These cylinders were
- rolled out of straight plates and then
- welded longitudinally. By means of a U-
- butt joint the cylinders were joined
- together to form girders of up to 60
- metres in length. The main girders of
- the truss were supplied in 60-metre
- lengths. These sections were joined up
- at the construction site and the
- diagonals affixed between the girders.
- The diagonals of the open-frame consists
- of spiral-shaped welded pipes,
- constructed along the same lines as the
- cardboard tube inside a toilet roll.
-
- [Image] [Background]
- [Home] [Index]
-
- [Visitors' book]
- [photo of pipe]
-
- [photo train] Truss assembly
-
- Assembly at the construction site
- commenced with the positioning of
- temporary supports, on which the lower
- cylinder-girders of the truss were
- placed. Temporary supports or "A-
- frames" were then placed on the lower
- two main girders. Mobile cranes then
- lifted the upper girder sections into
- position, after which the diagonals
- were positioned between the upper and
- lower girders. The truss-sections were
- then welded together. On account of
- the wall-thickness (up to 90 mm) of
- the main girders, a single weld
- consisted of 102 layers, taking
- approximately 160 welding-hours. To
- permit welding under controlled
- conditions and to prevent pollution of
- the surface waters, welding tents were
- positioned around these connection-
- points, with lighting and dust-
- exhaustion facilities.
-
-
- [Image]
- [Backward] [Home]
-
- [Index]
- [Visitors' book]
-
- [photo of wall]
-
- Attachment of the trusses to the
- retaining wall
-
- The trusses are attached to the retaining
- wall when the latter is floating. By the
- admission of ballast water into the gate,
- by controlling the dock and outer water
- level and by manoeuvring with the aid of
- winches, the retaining wall is positioned
- in such a way that the first three main
- girders of the truss can be attached. The
- main girders were fixed in position by
- means of clamps. The retaining wall is
- once again manoeuvred in such a way that
- the three remaining main girders can be
- affixed in the correct position. All the
- main girders are then welded to the
- retaining wall. Finally the clamping
- structures are removed and the remaining
- diagonals, bottom props and the coupling-
- girder are positioned.
-
- [Image] [Backward]
- [Home] [Index]
-
- [Visitors' book]Operation of the Storm Surge Barrier
-
- Wetted works (sill structure)
-
- The sill structure on the bottom of the
- New Waterway has three functions:
-
- * The formation of a flat base and
- foundation for the retaining walls,
- which are positioned on the sill-
- blocks with the aid of fenders.
- * Cutting down the flow of water once
- the barrier is closed.
- * Holding in place the subgrade on
- which the blocks are based.
-
- 1. Sill-blocks
- 2. Bottom protection and filter-bed
- 3. Dredging works
- 4. Raking the surface
- 5. Dumping the filter-bed
-
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- [Image]
- [Backward]
- Wetted works sill-blocks
-
- A total of 64 sill-blocks have been
- installed on the bottom of the fast-
- flowing New Waterway at an average
- distance of 3.5 centimetres apart. The
- blocks were delivered by pontoon and
- positioned with the aid of a floating
- derrick. Various measuring instruments
- were used to enable the blocks to be
- positioned to within one centimetre.
- A 21-metre-high measuring tower was
- attached to each block, which remained
- just poking up above water after the block
- had been sunk into position.
-
- Since the sills are somewhat curved, the
- blocks are slightly wedge-shaped. In
- cross-section the blocks are also flared,
- thus preventing the tops of the blocks
- from "rubbing" against each other in such
- a way as to create a larger crack at the
- bottom than permitted. Two rubber toes
- have been fitted on one side of each
- block, with corresponding notches on the
- other side. [Home]
- [Index]
-
- [Visitors' book]Wetted works - bottom protection and
- filter-bed
-
- It was not possible for the sill-blocks to
- be simply placed direct onto the river-
- bed: rapid accelerations in current would
- otherwise create major turbulence beneath
- and in the vicinity of the blocks upon
- closure of the barrier. Furthermore the
- sill could be seriously destabilised if
- water were unable to pass beneath the sill
- blocks. For this reason the blocks rest on
- a porous filter-bed, in turn resting on
- substantial bottom-protection.
-
- Filter-bed
-
- Length: 60 metres
- Weight: 206 MN (206,000 tonnes)
- various materials,
- distributed over four layers:
- layer 1 sand 0.5-5 mm
- thickness 0.5 m
- (bottom layer)
- layer 2 gravel 3.5-35 mm
- thickness 0.5 m
- layer 3 (basalt) 30-140 mm
- thickness 0.5 m
- layer 4 rubble (basalt) 10-60 kg
- thickness 0.75 m (top
- layer)
-
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
- Wetted works - dredging works
-
- In order to install the filter-bed and the
- bottom-protection, the new Waterway was
- dredged out from a depth of 14.5 metres
- below Amsterdam Ordnance Datum (NAP) to a
- maximum depth of 22.5 metres below NAP. In
- total 920,000 cubic metres of sand and
- sludge were dredged up. With the
- installation of the filter-bed the bottom
- was raised to a level of 17 metres below
- NAP.
-
- Three kinds of dredging vessels were used:
-
- * The tow-hopper for the coarse-
- dredging of the cunette (trench) in
- the New Waterway. A backhoe or grab
- was used to dredge the slopes.
- * The dustpan suction-dredger for
- smoothing the cunette and installing
- the bottom filter-layer.
- * The inclined stone-tipper for dumping
- the bottom protection and the other
- two filter-layers.
- [Image]
- [Background]
-
- [Home]
- [Index]
-
- [Visitors' book]
-
-
-
-
-
-
- [Image]
- [Backward]Wetted works - raking out
-
- A good seal was needed between the filter
- bed and the sill blocks. This was achieved
- by smoothing the top layer of the filter-
- bed. To this end a steel device with
- vertical teeth was mounted on the mouth of
- a dustpan suction-dredger to create a kind
- of rake. Following the good results
- obtained with a similar method on Neeltje
- Jans and in the Petroleum Harbour in the
- Europort area, this method was also
- applied in the New Waterway.
- [Home]
- [Index]
-
- [Visitors' book]
- Wetted works - dumping the filter-bed
-
- After extensive research it was considered
- feasible to dump the various filter
- materials on the river bed. This procedure
- involved two risks:
-
- * the risk of separation of the filter
- material (with larger particles
- becoming separated from smaller),
- thus potentially reducing the
- stability of the filter-bed.
- * the risk of mixing in sand when the
- filter material was dumped; the
- deposition of sludge between the
- various layers also reduces the
- stability of the filter-bed.
-
- Special measuring techniques were used in
- the dumping-process. It proved possible to
- dump the various layers on each other to
- within 10 centimetres of the required
- thickness.
-
- Vessels
- Various vessels were used in installing
- the filter-bed. A dredge was fitted out in
- order to suck up sand and to dump coarse
- sand and gravel. Another vessel (Jetsed)
- squirted air and water jets to prevent any
- sludge from being deposited between the
- various layers. The Jetsed is a self-
- propelling vessel that removes sediment
- deposits in the cunette between the filter
- layers. This is achieved by vertical air
- and water injection, thus throwing up the
- disturbed sediment, which is then borne
- away in the tidal currents.
- [Image]
- [Backward] [Home]
-
- [Index]
- [Visitors' book]
-
- [animation]
-
- [animation]
-
- [animation]
-
- [animation]Operation of the Storm Surge Barrier
-
- Operating equipment and parking dock
-
- Upon closure of the barrier, operating
- equipment drives the retaining walls out
- of the parking dock to close the New
- Waterway. This equipment is operated from
- control buildings on the north and south
- sides. The equipment consists of three
- elements: the operating equipment of the
- dock-gate, the locomobile and the ballast
- system in the retaining wall.
-
-
- [Image]
- [Backward] [Home]
-
- [Index]
- [Visitors' book]
-
- [photo of dock]
-
- [photo of dock]
-
- Operating equipment parking dock
-
- [detail of parking dock]
- The parking dock protects the retaining
- wall when the Storm Surge Barrier is
- retracted, thus creating a protected
- harbour for the retaining wall. When
- inside the dock the retaining wall cannot
- be rammed by passing vessels. With this
- in mind the dock has also been fitted
- with a special, extremely robust gate.
-
- One of the great advantages of the
- present Storm Surge Barrier design is
- that when at rest, the parking docks are
- dry, so that maintenance activities can
- be easily carried out. To facilitate
- maintenance still further, 14 concrete of
- support points have been installed in and
- beside the dock, thus leaving the wall
- some 2.5 metres off the floor of the
- dock.
-
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
- [animation]
- Operating equipment - dock-gate
-
- [dock-gate]
- The dock-gate is designed to seal off the
- dock. In addition the dock-gate protects
- the retaining wall from being run into by
- vessels; the gate has been designed in
- such a way that vessels scraping the gate
- are warded off, while also providing
- maximum protection in the event of a head-
- on collision. The dock-gate may be
- compared with a safe-door (dimensions: 2 m
- thick, 12 m high and 20 m long), running
- backwards and forwards over a rail. Since
- sludge builds up on the rail, the dock-
- gate is opened once a month for the sludge
- to be bulldozered off.
-
- The dock-gate is opened immediately before
- the retaining wall is propelled into the
- main stream. Once the closure has been
- completed the dock-gate seals off the
- parking dock again.
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
- [animation]
-
- [animation]
-
- [animation]
- Operating equipment - the locomobile
-
- [locomobile]
- In order to close the barrier, the
- locomobile on top pushes the retaining
- wall horizontally out of the parking dock.
- Upon completion of the closure the
- locomobile draws the retaining wall back
- into the dock. With the aid of running and
- guide wheels on railtracks, the locomobile
- rests with its own weight on the upper
- side of the retaining wall. It pushes off
- against the control tower and transmits
- its force to the retaining wall by means
- of a rack and pinion. The toothed wheels
- are constructed out of high-grade chrome
- nickel steel. The rack runs the entire
- length of the door.
-
- In the rest situation the locomobile also
- keeps the retaining wall in position
- horizontally.
- [Image]
- [Backward]
-
- [Home]
- [Index]
-
- [Visitors' book]
- Operating equipment - ballast system
-
- During closure the retaining walls move in
- two directions. Apart from the horizontal
- movement out of the parking dock the walls
- also move up and down in the waves when
- being sunk and refloated. The ballast
- system in the retaining wall facilitates
- the sinking and refloating of the
- retaining wall. When the remote-controlled
- inlet-valves are opened, water flows into
- the specially designed ballast tanks in
- the retaining wall. In order to ensure
- that the wall sinks stably, the water must
- flow into all the tanks evenly.
-
- Pumps set in the retaining wall expel the
- ballast water from the retaining wall when
- the latter needs to be raised again. Each
- retaining wall is fitted with 30 pumps and
- 14 chaser-pumps to remove the last
- remaining water. The capacity of the pumps
- varies from 1.6 kW to 40 kW.
-
-