Details
By default, eSuite scheduler assigns a duration of one day to each task, where one day is defined as 8 hours of work. You can change any task duration, either as you enter the task or at a later time.
You can specify task duration using any of the following time units:
eSuite scheduler automatically adjusts to the next larger time unit as you type a duration that can be expressed as a larger time unit. For example, "65m" appears as "1h 5m," and "12h" appears as "1d 4h."
If you know how many days a task has been in progress, you can display its progress by entering the duration to date. When you enter the actual duration of a task, eSuite scheduler updates the actual start date, the percentage of the task that is complete, and the duration of the task remaining in the schedule.
See also
Planning a project
Adding project tasks
Entering start and end dates
Linking and unlinking tasks
Creating a task hierarchy
Adding columns to to the schedule
Displaying a task's percentage complete